Church Meeting: BUILD update and vote on proposal 31 March 2011

+1

No comments posted yet

Comments

Slide 1

Update on progress LRBC Church meeting 31st March 2011

Slide 2

The journey continues….. The background…. 98 out of 100 supported the proposed resolution on the 18th November Church Meeting. BU loan up to £620,000 Cory grant £55,000

Slide 3

Tender Process 5 Contractors. All tenders over budget. Focused on working with the lowest tender contractor.

Slide 4

Lowest Tender Project Target cost £ 900,000 Tender submission £1,088,000 Over budget £ 188,000 Includes VAT and contingency

Slide 5

Tender Process part 2 Key area of over spend - mechanical Instructed investigation into savings Construction savings £78,000 M&E design unchanged

Slide 6

Project Costs Project Target cost £ 900,000 Tender submission £1,088,000 Over budget £ 188,000 _____________________________________________ Construction savings £ 78,000 M&E design unchanged Final tender cost £1,010,000

Slide 7

Funding Gifts & Pledges (Feb11) £683,000 Includes Housing Association and Cory pledges BU Corp. Loan £620,000 Current pledges cover 5.5 years repayments at current interest rate General giving is healthy

Slide 8

Proposal Enter a contract with TJ Evers for a total project cost of £1,010,000. Resolution from January’s Church Meeting empowering Trustees to sign contract still stands.

Slide 9

Reminders Gift aid: 28p to 25p from 6th April 2011 so please give now if you are able. Legacy Keep on fundraising!

Summary: An update on progress for Leigh Road Baptist Church BUILD project as given by Jane Brookes at the church meeting 31 March 2011. The proposal was passed.