BUILD update on progress 26 May 2011

0

No comments posted yet

Comments

Slide 1

Update on progress LRBC Church meeting 26 May 2011

Slide 2

The journey continues….. The main contractor T.J. Evers took possession of the site on Tuesday 3 May. The contractual completion date is Monday 5 December 2011

Slide 3

Site Set Up Part of the church garden is now the Contractor’s compound. The other part has been made safe for the Pre-school children to play in

Slide 4

Programme Work has commenced in the boiler room. The old boiler has been removed and new boilers will be installed over the coming weeks.

Slide 5

Programme Demolition works started on Wednesday. The first job is to strip the premises of timber Next week the demolition of the Parlour will commence.

Slide 6

Programme The first Site Meeting takes place on Wednesday 1 June. The Development Team are meeting with the architect on Thursday 9 June to agree and finalise areas of savings

Slide 7

Outstanding issues Fan convector heaters in the Sanctuary Garden

Slide 8

Funding Gifts & Pledges (May) £711,000 Includes Housing Association and Cory pledges - 70.4% of total costs Grants – Garfield Weston Foundation CORY Agreement Fund-raising events

Summary: An update on progress for Leigh Road Baptist Church BUILD project as given by Jane Brookes at the church meeting 26 May 2011

Tags: build lrbc church meeting

URL:
More by this User
Most Viewed